 |
CONTRACT DOCUMENTS THAT LEAD TO CHANGES, CHANGE ORDERS, AND DISPUTES
INTRODUCTION
Each construction project is a unique combination of countless design
details, materials, and individual efforts. Despite the uniqueness of each project, there is one constant in construction --- change and the need to anticipate the unexpected.
This article, which was originally authored by Steve Holloway and published by Aspen Publishers in Chapter 3 of the 2006 Construction Law Update, describes recurring issues that tend to create changes and affect
construction. Due to their effect on cost and time of performance, these issues also frequently cause disputes among the owner, contractor, and designer, harming
relations and further adversely affecting construction.
This chapter provides a practical guide to alert all participants in the design
and construction process to the source of disruptive changes, and illustrate how to
anticipate and avoid them. This chapter is a practical guide to these issues, not a
definitive legal analysis of who bears legal liability for the changes. By being
better informed about the likely sources of changes, the parties may be able to
limit their impact on their projects and avoid costly and protracted disputes.
OVERVIEW OF ASPECTS OF CONTRACT DOCUMENTS THAT CONSISTENTLY PRODUCE CHANGE ORDERS
Change orders are a normal part of construction projects. Their occurrence
is not so much a question of ‘‘if’’ as of ‘‘when, where, how many, and how much.’’
Although it may seem a bit counterintuitive to some, change orders are not necessarily "bad things", as many
contractors view change orders as sources of revenue and profit. Consistent sources of change orders in contract documents include:
- Defective Specifications;
- Illegal Restrictions;
- Improvements in Time;
- Incomplete Design;
- Intention of the Contract Documents;
- Lack of Design Discipline Coordination;
- Latent Conditions;
- Owner Changes; and
- Updated Information
This article addresses only Defective Specifications. Subsequent articles will address Illegal Restrictions and the other sources of changes.
Defective Specifications
The term defective specifications is common throughout the industry and generally
refers to specifications containing errors and/or omissions. The resultant
contract changes are of the type that are often approved by the owner without great
objection. Common types of defective specifications include:
- Copied specifications
- Expired specifications;
- Generic specifications;
- Impractical specifications;
- Multiple specification interpretations; and
- Nondisclosure
Copied Specifications
Whether prepared manually or electronically, most specifications begin with
a generic format. The specification might be one that the architect used on a past
project or it might be a commercially prepared standard format, such as those
produced by the Construction Specifications Institute (CSI).
In any case, specifications are rarely prepared totally from scratch or solely for a specific project.
Principal factors that increase the probability that copied specifications will
result in errors in the contract documents include:
- The engineering, design, and construction drawings are the primary focus of the design team and the owner, and
- The technical specifications tend to be a secondary priority and little attention
is given them until the design is complete.
Under such circumstances, copying and editing an existing specification is often viewed as the obvious and easiest method
of preparing specifications. Second, once the design is complete, the owner is eager to get construction underway and specifications are often assembled at the
last minute. Copied specifications are not inherently defective or inappropriate, but when used improperly and assembled carelessly, they can lead to changes and problems
during construction.
Expired Specifications
In an age of ever-changing building products, many product specifications
have a limited life span. The age of a specification can become a problem on public
projects, because these projects are subject to variations in political funding. Some
state and federal projects can be shelved for years while awaiting the political
climate that will allow them to proceed.
The amount of time a project is on hold increases the possibility that priorities
will change and that the people in the chain of command will have different
authority. Even the people who designed the job in the architect’s office may be
working for another firm and the project architect might even be out of business.
The net effect of all of this is that the original project concept may become
altered, and the bases for certain design decisions lost.
Generic Specifications
Generic specifications are similar to copied specifications in that they often
originate from a previous project. They can come from many sources, but common
examples include:
- Product requirements provided by manufacturers. A problem often arises
when several manufacturers are listed as acceptable, and the words ‘‘or equal’’ are
included, because ‘‘equal’’ manufacturers will often have different specifications.
If the differences are slight, they tend to go unnoticed. If differences are significant,
the contractor may be entitled to a change order if forced to provide the
specified item at an increased cost.
- Specifications provided by manufacturers. Architects may sometimes accept
a manufacturer’s offer to prepare sections specifying his or her product. As a
result, the final specifications might reflect the manufacturer’s preferred language,
rather than what the architect might have specified.
- Specifications written without a specific product in mind. On occasion,
specifications are written without a specific product in mind. Specific qualities
or requirements are listed, even though the architect has not confirmed that they
are available in a product currently on the market.
Impractical Specifications
Designers tend to follow old habits, sometimes fitting together components
without due consideration for construction means and methods, or not properly
coordinating an item with adjacent work. Design conflicts sometimes result
in specifications that are needlessly difficult, and sometimes impossible, to
build. Examples of this situation include:
- Foundation wall design configurations that did not allow removal of form work;
- Concrete anchors that were designed and installed in inaccessible areas;
- Equipment that could not be reached by available access routes;
- Illogical and needlessly costly construction sequences; and
- Equipment that could not be accessed for maintenance after installation.
Multiple Specification Interpretations
In general, if a specification is subject to more than one reasonable
interpretation, the contractor has the right to choose one of those interpretations.
Such inconsistencies have taken the form of:
- Discrepancies between requirements of the plans and specifications;
- Differences between small and large drawing details;
- Differences between initial and final finish schedules;
- Differences in plan dimensions among design disciplines; and
- Differences between the actual equipment cut sheets and those details originally
shown in the contract.
Nondisclosure
Nondisclosure refers to the failure to inform a contractor of design or construction
information that is or may be significant to the pricing and completion of
the work. Such nondisclosure can be inadvertent or can be intentional for fear that
it would lead to a corresponding increase in price. Depending on the terms of the
contract and applicable law, the contractor may be entitled to additional time and/
or compensation due to the nondisclosure. Examples from previous cases of the
type of critical information that was withheld and caused unanticipated financial
hardship on the contractor and hindrances to the project include:
- Changes in the owner’s construction financing that affected the timing and
amount of progress payments;
- The presence of undisclosed bedrock in areas of excavation;
- The presence of organic material with unsuitable bearing capacity that was not
noted in the geotechnical investigation or report; and
- Restricted staging, lay-down, and site access that caused damage, increased
costs, and reduced worker productivity.
Unintentional nondisclosure can be the result of a deficiency in the design
effort or simply the failure of an owner to understand the significance of the
information to the construction process. Intentional nondisclosure can stem
from any number of self-serving causes. In either case, the contractor may be
unfairly denied the opportunity to consider the information at the time of bid.
Closing
This article has addressed the elements of defective specifications that have consistently produced changes and disputes. Subsequent articles will address Illegal Restrictions and other sources of changes.
|
 |
Visit Our Web site
Our Services

"It's All About Damages"
Contact Information
The Holloway Consulting Group, LLC
10885 W. Beloit Place
Lakewood, Colorado 80227
Phone: (303)984-1941
Fax: (303) 716-0432
E-mail: holloway@hcgexperts.com
|
|