A sample text widget

Etiam pulvinar consectetur dolor sed malesuada. Ut convallis euismod dolor nec pretium. Nunc ut tristique massa.

Nam sodales mi vitae dolor ullamcorper et vulputate enim accumsan. Morbi orci magna, tincidunt vitae molestie nec, molestie at mi. Nulla nulla lorem, suscipit in posuere in, interdum non magna.

CONSTRUCTION EXPERTS | SCHEDULE ACCELERATION | CONTRACT PROVISIONS

Holloway Consulting is a construction schedule acceleration claims expert, and this is the second in our series of articles on this popular construction contractor claim entitlement.

CONSTRUCTION PROJECT SCHEDULE ACCELERATION

Contract Provisions

Both standard-form AIA contracts and custom agreements typically allow the owner and/or his agents to accelerate the schedule, completion date and time of performance. When the contractor is directed to complete the work in advance of the contract completion date, and the directive is in writing and signed by the owner, contracting officer or a duly authorized owner representative, the directive usually represents a change under the contract and the contractor’s claim for an equitable adjustment should involve only the usual change claim considerations.

The same result will follow even if the change or change order is not formalized by the owner as required by the contract. This is true even if the owner believes he/she is issuing such an order pursuant to his rights under other provisions of the contract which allow him/her to direct the contractor to improve his performance at no cost to the owner.

It is sometimes difficult for the construction contractor to ascertain whether or not a constructive acceleration order has been given, since often there is no direct, written order issued. This is an important element of the construction schedule acceleration entitlement, since a necessary component of (compensable) acceleration is the requirement of the contractor to complete, or attempt to complete, the work before the time to which he is entitled.

Of course, if the contractor accelerates the work to overcome non-excusable delays, the acceleration-related contract provisions of the agreement are not relevant.

READ MORE ABOUT SCHEDULE ACCELERATION HERE . . .

The Holloway Consulting Group, LLC – Construction Experts
International : (888) 545-0666

Email: steve.holloway@disputesinconstruction.com

____________________________________________________________________

See Selected Pages at Disputes In Construction.com, 12-21-11

  • Implied Warranty
  • Labor Strikes
  • Claims Consultants Schedule Delay Critical Path Methods
  • Suspension Of The Work
  • Labor Productivity
  • Disputes Claims Consultants
  • Defects Damages
  • Damages Expert Hoover Dam Bypass Bridge
  • Delay And Disruption Of Claims
  • Construction Expert Witness
  • Schedule Delay Experts Time Impact Analysis
  • Construction Contractor Consulting
  • Damages Experts | Holloway Consulting
  • Defects Expert | Cost of Repairs
  • Defects Expert Construction Failures
  • Defects Expert Custom Home Framing
  • Colorado Louisiana Experts
  • Defects Expert Site Design Issues
  • Defects Expert Post-Tensioned Concrete Decks
  • Schedule Delay Experts Cause-Effect Analysis
  • Expert Witness Resort Construction
  • Curtain Wall and Window Wall
  • What Types of Construction Claims?
  • Disputes Mediation And Arbitration Services
  • Claims Terminology?
  • Recent Cases
  • Resorts Hotels
  • Comments are closed.